Starting the Construction of the First Buildings in Bismayah New City Project
The process of building the first housing units had started in Bismayah New City project in the beginning of March.2014 as it started with compacting the concrete pillars in the soil followed by constructing the foundations of buildings.
The project technical manager said that the company had finished the process of installing the foundations concrete (Socle) which is one kind of the pre casting concrete laid over foundations in order to make the platforms for first floor of each building after installing the hollow concrete segments over the foundations, adding that the sandwich panel walls had also been installed which represent the external walls of the housing units.
Worth mentioning that Hanawah South Korean implementing company had launched the real production of the pre casting concrete in the PHC pile production factory that shall produce the platforms and ceilings for the housing units, knowing that the factory consists of four production lines automatically run.